How to add Tasks to a Share-Board / Project?
Step 1: Whether it’s a new or existing Project, adding tasks will be the same. Let’s add a task to an existing Project. Here in the Dashboard, we’ll choose the project “Test Project (3356)”


Step 2: When the project opens, we’ll be directed to the Task table.


Step 3: Click the first row – For Approval

Step 4: To add a task, click the buttons below the table. We’ll focus on the buttons #4 and #5.

Since we’re adding a task under the “For Approval” row, we’ll click the #5 button.

Step 5: It will add a row below the “parent row.” Use the slide bar to go through the row.
Fill in the following:
- Task Name
- User: who to assign to
- Priority: Low, Normal, High, Urgent
- Start date: Click the Calendar
- Due date: Click the Calendar
- Percentage of Completion
- Description: What the task is about, instructions, and other details
- Estimated (hrs): No. of hours to complete the task
- Approval: If approval is needed. (will only apply if USER is provided – who will approve)




Notice that the row is in “green” indicating a newly added row. When everything is filled in, don’t forget to save
. We named the task “New Asset.”

When the tasks is saved, the row will be white with green ID – indicating an update has been done in that row. The Action Icons will also appear when the tasks is saved.